Templeton Elementary

Templeton ES Project Scope

Community Meetings & Stakeholder Input

  • The design efforts for the Templeton Elementary rebuild have depended on stakeholder input in several forms. 

    Templeton & Twality - Individual /Combined Design Committees 

    A stakeholder team comprised of staff and community members, identified by the Principals from both schools, were convened to weigh decisions and help ensure no unfair bias towards an individual interest group. Design Committees met individually and together at separate stages of the project to discuss site / landscaping, transportation and other mutual design decisions. 

    Design Committe Charter

    Meeting Date Minutes
    Templeton Meeting #7 4/27/2017 Minutes
    Templeton Meeting #6 3/14/2017 Minutes
    Combined Meeting #5 3/2/2017 Minutes
    Combined Meeting #4 2/16/2017 Minutes
    Combined Meeting #3 2/2/2017 Minutes
    Combined Meeting #2 1/26/2017 Minutes
    Combined Meeting #1 1/23/2017 Minutes

    Community Meetings 

    Workshops and Neighborhood Meetings were held at outset to introduce community to the project and provide a platform steering early design decisions.

    Meeting Date Presentation Minutes
    LU Neighborhood Meeting 7/6/2017 Presentation Minutes
    Community Workshop 3/4/2017 Presentation  


    Focus Groups 

    Focus Group meetings have been convened with staff, grouped by subject matter and interest, as an opportunity for smaller group discussion and more detailed conversation on individual program needs. These have occurred for each “phase” of the project for staff to evaluate and refine the design of their areas. 

     

Project Details

  • Architect | DOWA-IBI Group
    General Contractor |
    Triplett Wellman (New)
    GNC Construction (Core)

    Groundbreaking | June 2018
    Anticip. Completion | Aug 2019
    Budget | $29 Million

    Status | Construction

    * Dates are subject to change

Timeline

  • Nov 2016 - Bond Passed
    Jan 2017 - Programming Kick-off
    May 2017 - Schematic Design
    Jun 2017 - Design Development
    Dec 2017 - Construction Docs
    June 2018 - Groundbreaking
    June '18 - Aug '19 - Construction
    Fall 2019 - Construction Complete

Connect With Us

  • For more information about the TTSD Bond or individual projects:

    TTSDBondProgram@ttsd.k12.or.us
    Phone: 503-431-4000
    Tweet: @TigardTualSD
    Instagram: @TTSD_Builds

TMP Documents

  • Templeton Site Plan TMP Floor Plans    

    Templeton / Twality Site Plans - 7/2017

    Templeton Floor Plans - 11/2017