Tigard High School

Community Meetings & Stakeholder Input

  • The design efforts for the Tigard High School modernization have depended on stakeholder input in several forms.

    THS Design Committee

    A stakeholder team comprised of staff and community members, identified by the Principal, to weigh decisions and help ensure no unfair bias towards an individual interest group.

    THS Design Committe Charter

    Meeting Date Presentation Meeting Minutes
    Meeting #5 12/12/2017 Presentation Minutes
    Meeting #4 9/13/2017 Presentation Minutes
    Meeting #3 4/25/2017 Presentation Minutes
    Meeting #2 4/5/2107 Presentation Minutes
    Meeting #1 3/8/2017 Presentation Minutes

    Community Meetings

    Workshops and Neighborhood Meetings were held at outset to introduce community to the project and provide a platform steering early design decisions.

    Meeting Date Minutes
    Land Use Neighborhood Meeting 9/13/2017  Minutes
    Community Open House 6/1/2017  Minutes
    Community Workshop 4/8/2017 Minutes


    Focus Groups

    Focus Group meetings have been convened with staff, grouped by subject matter and interest, as an opportunity for smaller group discussion and more detailed conversation on individual program needs. These have occurred for each “phase” of the project for staff to evaluate and refine the design of their areas.

    Schematic Design: Room Surveys & May 8, 2017
    Aerobic/Cardio, CE2, Ceramics, Counseling, Fitness Center, Girls Locker Room, Health Classrooms, History & English, Locker Rooms, Main Office, Marketing & Business, Math, Multimedia, Small Gym, Student Services, Team Rooms, Weight Room, Kitchen, IT

    Design Development: October 2 - 6, 2017
    Auto Shop/ Robotics, Counseling, CTE, Administration, CE2, PE, Athletics, Academics, Electrical, IT, Kitchen, Maintenance

    Construction Documents/Furniture: TBD

Project Details

  • Architect | Bassetti Architects
    General Contractor | LCG Pence

    Groundbreaking | June 2018
    Anticip. Completion | TBD
    Budget | $66 Million

    Status | Construction

    * Dates are subject to change

Timeline

  • Nov 2016 - Bond Passed
    Dec 2017 - Programming Kick-off
    June 2017 - Schematic Design
    Dec 2017 - Design Dev.
    Apr 2018 - Construction Docs
    June 2018 - Groundbreaking

    2020 - Phase 2 construction
    June 2020 - Construction Complete