Durham Elementary

Durham Entrance

Project Details

  • Architect | BORA Architects
    General Contractor | Inline

    Groundbreaking | June 2019
    Anticip. Completion | Oct 2019
    Budget | $1.3 Million

    Status | Completed

     

Timeline

  • Nov 2016 - Bond Passed
    Dec 2016 - Programming Kick-off
    Jan 2017 - Schematic Design
    Feb 2017 - Design Dev.
    Mar - Oct 2018 - Project Hiatus
    Nov 2018 - Construction Docs

    June 2019 - Groundbreaking
    June - Sep 2019 - Construction
    Sep 2019 - Construction Complete